Organization and Procedures of Structural Planning

Architectural
Planning
Executive
Planning
Production Scheme

The organisational structure of the office as well as the structural calculation procedure for any building can be briefly described as follows:

Simply put, to facilitate exposure  we refer to the building plan (intended for living area, kitchen and bathrooms) within normal average structure both on plan and in raising,  constituted by chassis of n 5X8 spans of medium length; therefore a plotted surface of approximately 1000 m2; that is 4 floors outside and one basement.

 "Definitive input" is the definition of all the data needed for starting the structural planning:

·        availability of architectonic definitive plan (primarily clarity between the architectonic and structural planners regarding at least the  problems concerning for example the positioning of  vertical structural elements, staircase landings, the structural tipology of width and depth, and so on);

·        availability of the all geotechnical data;

·        availability of all data concerning the loads.

The first phase of structural planning is made of predimensioning, preparation of calculation input, automatic processing and up to the ultimate definition of all the verified structural elements of the elevation and the foundations, therefore verified both in positioning and in dimensions. This phase results in the output of the definitive structural works of the building.

The attached chart indicates  average working timeline for the planning of first phase, valued in 6 work days approximately.

The final product of the first (that provides the possibility knowledge of the "quarterdecks") is:

·        definition of the metric estimate of the building structures (calculating the incidence of the scaffolding in Kg/m3);

·        The invite to the structural plan to the system planner and architectonic planner for have note of eventual modifications to affix and for in order to carry out  the architectonic control for varying eventual (presumably not substantial).

We indicate this points like 2° phase, whose duration is only for the first point employee from the productive capacity of the Studio.

The 3° phase is constituted from executive structural planning, consequent to the introduction of last and definitive architectonic and system input, from which they gush:

·        last structural input (if have been approved of the modification) automatic elaboration, verifications, graphical elaboration of all the structural elements whit the armors relative.

·        Metric compute detailed estimativo with development of irons.

The duration this phase can be estimated medium in 5 work days.

 

In the event in which the volume of the commissioned work increased they can distinguish 2 cases:

A.     Buildings of similar dimensions that indicated for example, but of greater number.

B.     Only building of greater volumetric.

In the event A to the increment of the times is not directly proportional them to the increment of the number of manufatti, given the possibility to sovrapporre, with operating various to serial the points work,   the fasi of input and elaboration.

Medium we can indicate come ragionevole produttivitą, un raddoppio dei tempi per un triplicarsi delle progettazioni da effettuare.

In the event B ( o however in the event of ulterior number increment  of volumetric to calculate, that is for an ulterior expansion di quanto descritto nel previous point) the Studio has the possibility to resort to 2 external supports down (one relative of graphical elaboration, one relative of numerical elaboration) 30% approximately the proportionality directed between increment of the times rispetto to the indicated volumetric increment in the attached outline.

Relatively to other types of structural calculation (for example the recovery functional di building existing) corrected analysis of the relative times the delivery  to the executive plan can be carried, only one volta nota la tipology of the building and the partecipation.